[单选题]

( ) is a method used in Critical Path Methodology for constructing aproject schedulenetwork diagram that uses boxes or rectangles, referred to as nodes, torepresent activities andconnects them with arrows that show the logical relationships that existbetween them.

A.PERT

B.AOA

C.WBS

D.PDM

参考答案与解析:

相关试题

is a method used in Critical Path Method

[单选题]is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exis

  • 查看答案
  • is a method used in Critical Path Method

    [单选题]is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles,referred to as nodes,to represent activities and connects them with arrows that show the logical relationships that exist

  • 查看答案
  • (73) is a method used in Critical Path

    [单选题] (73) is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships tha

  • 查看答案
  • is a method of constructing a project sc

    [单选题]is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies

  • 查看答案
  • (1) is a method of constructing a projec

    [单选题,共用题干题] (1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of de

  • 查看答案
  • One method of constructing large marine

    [单选题]One method of constructing large marine diesel engines and reducing the total engine frame weight is through ().A . casting interlocking componentsB . welding plates to form sections for assemblyC . forging integral componentsD . case hardening integ

  • 查看答案
  • N£­S diagram can used to substitute conv

    [单选题]N-S diagram can used to substitute conventional program flow Chart.In the following phrases,Which does not belong to the basic control structures that contain?A.sequence structureB.condition StructureC.selection structureD.execution structure

  • 查看答案
  • When ‘Final’ is used in class, method an

    [主观题]When ‘Final’ is used in class, method and property, what dose itmean?

  • 查看答案
  • critical-point drying method(临界点干燥)

    [名词解释] critical-point drying method(临界点干燥)

  • 查看答案
  • Which of the following techniques is NOT used in the Grammar—Translation Method?

    [单选题]Which of the following techniques is NOT used in the Grammar—Translation Me

  • 查看答案
  • ( ) is a method used in Critical Path Methodology for constructing aproject schedulenetwork diagram