[单选题,共用题干题]

(1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity.

空白(1)处填()

A .PDM

B . CPM

C . PERT

D . AOA

参考答案与解析:

相关试题

is a method of constructing a project sc

[单选题]is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies

  • 查看答案
  • One method of constructing large marine

    [单选题]One method of constructing large marine diesel engines and reducing the total engine frame weight is through ().A . casting interlocking componentsB . welding plates to form sections for assemblyC . forging integral componentsD . case hardening integ

  • 查看答案
  • ( ) is a method used in Critical Path Methodology for constructing aproject schedulenetwork diagram

    [单选题]( ) is a method used in Critical Path Methodology for constructing aproject

  • 查看答案
  • In multi£­phase projects, the () Projec

    [单选题] In multi-phase projects, the () Project process closes out the portion of the project scope and associated activities applicable to a given phase.()A.Scope B.Plan C.Close D.Control

  • 查看答案
  • The (74) technique involves using projec

    [单选题]The (74) technique involves using project characteristics in a mathematical model to predict total project cost models Can be simple or complex.A.reserve analysisB.cost aggregationC.parametric estimatingD.funding limit reconciliation

  • 查看答案
  • is a method used in Critical Path Method

    [单选题]is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exis

  • 查看答案
  • is a method used in Critical Path Method

    [单选题]is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles,referred to as nodes,to represent activities and connects them with arrows that show the logical relationships that exist

  • 查看答案
  • What is the most appropriate test statistic for constructing confidence intervals for the population

    [单选题]What is the most appropriate test statistic for constructing confidence int

  • 查看答案
  • When constructing a confidence interval for the population mean of a nonnormal distribution when the

    [单选题]When constructing a confidence interval for the population mean of a nonnor

  • 查看答案
  • method of moment

    [名词解释] method of moment

  • 查看答案
  • (1) is a method of constructing a projec