[单选题]

The (73) provides the project manager with the authority to apply organizational resources to project activities.

A.project management plan

B.project charter

C.project human resource plan

D.project stakeholders

参考答案与解析:

相关试题

The( )provides the project manager with

[单选题]The( )provides the project manager with the authority to apply organizational resources to project activities。A.project management planB.project charterC.project human resource planD.project stakeholders

  • 查看答案
  • The( )provides the project manager with

    [单选题]The( )provides the project manager with the authority to apply organizational resources to project activities。 A.project management plan B.project charter C.project human resource plan D.project stakeholders

  • 查看答案
  • The()provides the project manager with t

    [单选题]The()provides the project manager with the authority to apply organizational resources to project activities.A . project management planB . contractC . project human resource planD . project charter

  • 查看答案
  • The(70)provides the project manager with

    [单选题]The(70)provides the project manager with the authority to apply organizational resources to project activities.A.project management planB.contractC.project human resource planD.project charter

  • 查看答案
  • The ( ) provides the project manager with the authority to apply organizational resources to project

    [单选题]The ( ) provides the project manager with the authority to apply organizati

  • 查看答案
  • The ( ) provides the project manager with the authority to apply organizational resources to project

    [单选题]The ( ) provides the project manager with the authority to apply organizati

  • 查看答案
  • To ensure the project team provides the

    [单选题]To ensure the project team provides the functionality the customerexpects in a new piece of software, the project manager ask the customer forsign-off on the design criteria. These documents are(75).(75) A. technical specificationsB. performance spec

  • 查看答案
  • A project manager believes that modify

    [单选题] A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should(75).(75)A.assign change tasks to project membersB.call a meeting of the configuration control boardC.chan

  • 查看答案
  • A project manager believes that modifyin

    [单选题]A. project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should______.A.assign change tasks to project membersB.call a meeting of the configuration control boardC.change

  • 查看答案
  • A project manager is called to an infor

    [单选题]A project manager is called to an informal meeting with the customer and a problem is raised. This problem has major implications for the project manager's company, but the customer wants to pursue a solution at the meeting.The project manager shoul

  • 查看答案
  • The (73) provides the project manager wi