[单选题]

The (74) technique involves using project characteristics in a mathematical model to predict total project cost models Can be simple or complex.

A.reserve analysis

B.cost aggregation

C.parametric estimating

D.funding limit reconciliation

参考答案与解析:

相关试题

The(72)technique involves using project

[单选题]The(72)technique involves using project characteristics in a mathematical model to predict total project costs. Models can be simple or complex.A.Cost AggregationB.Reserve AnalysisC.Parametric EstimatingD.Funding Limit Reconciliation

  • 查看答案
  • The()technique involves using project ch

    [单选题]The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.A . costaggregationB . reserve analysisC . parametricestimatingD . funding limit reconciliation

  • 查看答案
  • The ( ) technique involves using project characteristics in a mathematical model to predict total pr

    [单选题]The ( ) technique involves using project characteristics in a mathematical

  • 查看答案
  • ()involves using mathematical techniques

    [单选题]()involves using mathematical techniques to forecast future outcomes based onhistorical results.A . TrendanalysisB . QualityauditC . Defect repair reviewD . Flowcharting

  • 查看答案
  • (75) involves using mathematical techni

    [单选题](75) involves using mathematical techniques to forecast future outcomes based on historical results.(75)A. Trend analysisB. Quality auditC. Defect repair reviewD. Flowcharting

  • 查看答案
  • involves using mathematical techniques t

    [单选题]involves using mathematical techniques to forecast future outcomes based on historical results.A.Trend analysisB.Quality auditC.Defect repair reviewD.Flowcharting

  • 查看答案
  • Performing (74) involves monitoring sp

    [单选题] Performing (74) involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.(74)A. quality planningB. quality assuranceC. quality perform

  • 查看答案
  • Performing (74) involves monitoring spe

    [单选题]Performing (74) involves monitoring specific project results to determine if they compLy with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.(74) A. quality planningB. quality assuranceC. quality perform

  • 查看答案
  • Performing(74)involves monitoring specif

    [单选题]Performing(74)involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.A.quality planningB.quality assuranceC.quality performanceD.qual

  • 查看答案
  • In multi£­phase projects, the () Projec

    [单选题] In multi-phase projects, the () Project process closes out the portion of the project scope and associated activities applicable to a given phase.()A.Scope B.Plan C.Close D.Control

  • 查看答案
  • The (74) technique involves using projec