[单选题]

E.stimate activity durations is the processof estimating the number of work periods to complete indivities with estimatedresources . the tools and technques is not including().

A.expert judgment

B.analogous estimating

C.requiremen tstraceability matrix

D.three-point estimating

参考答案与解析:

相关试题

Estimating activity durations uses infor

[单选题]E.stimating activity durations uses information on activity scope of(74) , required resource types, estimated resource quantities, and resource calendars.A.milestoneB.baselineC.qualityD.work

  • 查看答案
  • Estimating activity durations uses infor

    [单选题]E.stimating activity durations uses information on activity scope of(74),required resource types,estimated resource quantities,and resource calendars.A.milestoneB.baselineC.qualityD.work

  • 查看答案
  • Estimating activity durations uses inf

    [单选题] Estimating activity durations uses information on activity scope of (74),required resource types, estimated resource quantities, and resource calendars.(74)A. milestoneB. baselineC. qualityD. work

  • 查看答案
  • Estimating activity durations uses infor

    [单选题]E.stimating activity durations uses information on activity scope of (74), required resource types, estimated resource quantities, and resource calendars.(74)A. milestoneB. baselineC. qualityD. work

  • 查看答案
  • Estimating activity durations uses infor

    [单选题]Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.A . milestoneB . baselineC . qualityD . work

  • 查看答案
  • Estimating activity durations uses information on activity scope of ( ) , requiredresource types, es

    [单选题]Estimating activity durations uses information on activity scope of ( ) , r

  • 查看答案
  • The Estimate Activity Resource process

    [单选题] The Estimate Activity Resource process is closely coordinated with the (73)process.(73)A. Estimate CostsB. Sequence ActivitiesC. Plan CommunicationsD. Conduct Procurements

  • 查看答案
  • The Estimate Activity Resource process i

    [单选题]The Estimate Activity Resource process is closely coordinated with the(73) process.A.Estimate CostsB.Sequence ActivitiesC.Plan CommunicationsD.Conduct Procurements

  • 查看答案
  • The Estimate Activity Resource process i

    [单选题]The Estimate Activity Resource process is closely coordinated with the(73)process.A.Estimate CostsB.Sequence ActivitiesC.Plan CommunicationsD.Conduct Procurements

  • 查看答案
  • The Estimate Activity Resource process i

    [单选题]The Estimate Activity Resource process is closely coordinated with the (73)process.(73)A. Estimate CostsB. Sequence ActivitiesC. Plan CommunicationsD. Conduct Procurements

  • 查看答案
  • Estimate activity durations is the proce