[单选题]

E.stimating activity durations uses information on activity scope of(74) , required resource types, estimated resource quantities, and resource calendars.

A.milestone

B.baseline

C.quality

D.work

参考答案与解析:

相关试题

Estimating activity durations uses infor

[单选题]E.stimating activity durations uses information on activity scope of(74),required resource types,estimated resource quantities,and resource calendars.A.milestoneB.baselineC.qualityD.work

  • 查看答案
  • Estimating activity durations uses infor

    [单选题]E.stimating activity durations uses information on activity scope of (74), required resource types, estimated resource quantities, and resource calendars.(74)A. milestoneB. baselineC. qualityD. work

  • 查看答案
  • Estimating activity durations uses infor

    [单选题]Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.A . milestoneB . baselineC . qualityD . work

  • 查看答案
  • Estimating activity durations uses inf

    [单选题] Estimating activity durations uses information on activity scope of (74),required resource types, estimated resource quantities, and resource calendars.(74)A. milestoneB. baselineC. qualityD. work

  • 查看答案
  • Estimating activity durations uses information on activity scope of ( ) , requiredresource types, es

    [单选题]Estimating activity durations uses information on activity scope of ( ) , r

  • 查看答案
  • The process of ( ) schedule activity durations uses information on schedule activityscope of work, r

    [单选题]The process of ( ) schedule activity durations uses information on schedule

  • 查看答案
  • Estimate activity durations is the proce

    [单选题]E.stimate activity durations is the processof estimating the number of work periods to complete indivities with estimatedresources . the tools and technques is not including().A.expert judgmentB.analogous estimatingC.requiremen tstraceability matrixD

  • 查看答案
  • Estimating schedule activity costs invol

    [单选题]E.stimating schedule activity costs involves developing an (74) of the cost of the resources needed to complete each schedule activity.A.accuracyB.approximationC.specificationD.summary

  • 查看答案
  • Estimating schedule activity costs invol

    [单选题,共用题干题] Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most applic

  • 查看答案
  • Estimating schedule activity costs invol

    [单选题]E.stimating schedule activity costs involves developing an(69)of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in most application

  • 查看答案
  • Estimating activity durations uses infor